maintained, both during the operation 
    of 11 marine sites impacting the river as well as the additional marine traffic generated by construction.  Crane barges, jack-up barges, project tugs and tows are involved, including the 
 
  construction sites, removing tunnel spoil and delivering building materials including the many thousands of segments which are linked together to line the tunnel. “This is essential as it will 
    help to minimise the impact of the scheme on local residents. 
 
  
The Greater London Authority (GLA) and Transport for London (TfL) support the 
use of the river to help keep lorries, 
with the associated pollution and safety 
    hazards, off London’s roads.
  
    “At the same time, we are starting to 
    get the river ready for construction, for example by installing moorings needed 
    for barges moving supplies to and from riverside sites.
  
    “From very early on we have urged 
    those overseeing the project to use 
    the river as much as possible – 
    whether it’s the movement of spoil, 
    sand, steel or indeed the huge boring machines that will create the tunnels themselves.
  
    “There was some resistance to 
    maximising the use of the river for transporting building materials, but 
    we have witnessed a steady increase 
    with the support of top executives at Tideway. For example, the moving of 
    tunnel segments will now be done entirely by barge And we’ve played a significant part in making sure that the river will be 
    the major route for construction traffic and we’re pleased to see that more material will be transported by river than road.
  
    “As one of the principal stakeholders, 
    we must work with the various 
    contractors to make sure they are 
    doing what we’ve authorised.”  
 
shipment of the tunnel 
  boringmachines, and have 
  to be safely manoeuvred at a 
  time of increasing passenger transport and recreational activity. 
  “So far, there hasn’t been that 
  much of an increase in river traffic, as just preliminary works are 
  taking place. As work picks up towards the end of the year, there will be a reduction in navigable water space on which passenger freight and recreational activities can take place. Peak freight activities in relation to the project are expected throughout 2018.” 
  Terry, along with the rest of our Tideway team, has faced a mountain of paperwork since our involvement started and he’s had 
  to focus on the three phases of preliminary works: The 
  construction phase, the 
  operational phase and the decommissioning phase. “I’ve enjoyed learning more about building on the Thames and the different construction methods 
  that have been deployed.” 
    
  Planning and Skills
  James says: “We have 
  consistently urged the increased use of the river for tunnel